Cone Zone 7-19-15

-A A +A

For more information about the projects listed below, email lacpw@lacnm.us, call 662-8150, or visit the “Projects” link at losalamosnm.us. Motorists are asked to slow down and use caution within the construction work zones.
This information is based on a schedule provided by the contractors and may change due to weather or other delays.
Western Area Improvements Phase 3:

• Roadway and utility work continues on 43rd Street and 44th Street, which includes water line tie ends and concrete work. Roads mentioned above will be closed except for local residents and emergency vehicles.
• Sidewalks from cul-de-sacs, including 43rd and 44th Streets are under construction. The county suggests pedestrians use other routes into park. Pathway from 43rd Street to Ridgeway will be under construction.
20th Street/Fuller Lodge Improvements:

• Star Paving will start construction on the 20th Street/Fuller Lodge Improvements Project on Monday. The Contractor will be closing the southbound lane and begin demolition of curb and gutter, asphalt and sidewalks on the west side of the road. The county said pedestrians will need to use the east side of 20th Street.
• The northbound lane will remain open for business access. Motorists may experience flagging operations. Work hours will be Monday through Friday, 8 a.m.-5 p.m. Services such as mail delivery, emergency services, trash and recycling collection will be maintained.
Golf Course Entrance:

Construction work at the entrance leading to the Los Alamos County Golf Course off of Diamond Drive will start Wednesday. While the entire entrance will be repaired as a result of this construction activity, only half of the entrance will be affected at any given time allowing for access to the facility. The work is expected to last approximately two weeks.