Construction Zone 07-17-11

-A A +A

Diamond Drive
Phase 4

Today the Contractor will close the Trinity leg next to the Episcopal Church, use Canyon.  
Eastbound Trinity Drive traffic from south bound Diamond or Western Area will be detoured  at Diamond to Canyon Road and 39th or Canyon and Oppenheimer. Consider using the Canyon and Oppenheimer detour to access Trinity Drive at a signalized intersection.  Northbound Diamond traffic may access Trinity via the slip lane in front of the hospital.
Northbound from the Bridge — Left turns are being allowed at Canyon Road; The right turn slip lane onto eastbound Trinity will be open. The left lane continues through the work zone.
Southbound from University Drive — Expect two southbound lanes south of Sandia.  The left lane is a left turn lane at Canyon Drive. No left turns at Trinity. Trinity will be closed to eastbound traffic — use Canyon.  The right lane is the through lane for traffic crossing the bridge, as well as right turns onto University, Canyon, Trinity, and West Road.  Left turns are allowed on West Road.  
Transit: The southbound Park and Ride bus stop between Trinity and West Road is open. The northbound Park and Ride bus stop has moved from in front of the hospital further east on Trinity, in front of the pink house. The southbound Atomic City Transit bus stop on Diamond Drive at the Lemon Lot is open. The bus stop north of Canyon near the Griffith Gym parking lot continues to be closed; use the bus stop near Orange.

Barranca Mesa Phase 2 Maintenance Project

A.S. Horner will pave Dos Brazos south. Expect flagging operations, no delays are expected.

Milling, Recycling
and Repaving Work
in White Rock
County Pavement Crews will begin milling, recycling and repaving work on Tuesday in White Rock. The following streets will be resurfaced; Ridgecrest, Kimberly (North of Rover), Rover (Carlsbad to SR4) and Meadowlane (Rover to Lejano).
Door hangers will be delivered to residents providing 48 hours notice about milling and repaving operations on their street. Residents are asked not to park vehicles in the roadway during milling and paving operations.
Motorists should expect lane closures with flagging operations. Limited access and minor delays should be expected. Work will occur between 8:00 a.m. - 5:30 p.m, Monday through Friday.

Gas Line Replacement Project In Quemazon

Brisa del Bosque will continue to be closed with westbound traffic diverted along Quemazon and west on Esperanza.   Crews are mobilized on the south side of Brisa del Bosque to replace a natural gas line.  Work is expected to continue during the daytime, throughout the week.
 
REDI-net Fiber Optic Project

REDI Net Fiber Installation — As part of the new REDI Net initiative benefiting Northern NM and Los Alamos, crews will be pulling fiber through previously installed conduit along Diamond Drive for the next few weeks.
They will begin working on Monday along Diamond Drive; work will be coordinated with the Diamond Drive Phase 4 contractor.