The Chemistry Metallurgy Research Replacement facility may be alive after all, but then again, maybe not.
Legislators are almost finished debating the defense authorization bill for FY 2013 and the language in the bill would mandate that the federal government construct the controversial facility by 2026.
The Obama administration and the National Nuclear Security Administration have deferred the project for five years.
According to Global Security News Wire, the administration has argued that delaying construction of the new CMRR facility by five years would save money without harming nuclear-weapon readiness, but the plan has received mixed reviews on Capitol Hill.
Some lawmakers sought to proceed on a schedule that would have construction completed by 2024, though a budget resolution Congress approved for the first half of the fiscal year that began on Oct. 1 included no funds for the project.
On Tuesday, however, a conference committee established to resolve differences between the House and Senate versions of the fiscal 2013 defense authorization legislation released a bill that would establish a legal mandate that the CMRR building be up and running within 14 years.
If you currently subscribe or have subscribed in the past to the Los Alamos Monitor, then simply find your account number on your mailing label and enter it below.
Click the question mark below to see where your account ID appears on your mailing label.
If you are new to the award winning Los Alamos Monitor and wish to get a subscription or simply gain access to our online content then please enter your ZIP code below and continue to setup your account.
| ZIP Code: | |