Cone Zone 07-21-13

-A A +A

White Rock Milling and Paving Operations:
Milling is scheduled on the following streets: Mimbres north and south of Meadow, Lejano, Isleta, Hacienda, Granada, Futura, Ensenada, Delicado, Chiquita, Bandolina, Altura, Alhambra, Balboa, Sierra Vista, and Cañada Circle. The contractor will begin milling on Mimbres on Monday, July 22, working through the streets in the above order. Milling operations are expected to take approximately one day for each street. Work hours will be 7 a.m. to 7 p.m.
Paving will begin on Monday, July 22, on the following streets: Louise followed by Bryce between east of Verbena to Meadow Lane. As work progresses next week, paving operations will move to Kayenta, both sides of Joya Loop, and then possibly Mimbres if time permits. Paving operations are expected to take approximately one day per street with work hours between 7 a.m. and 7 p.m. As the work approaches your street, please move all vehicles to off-street parking.
Eastern Area 2 Concrete, Paving & Utility Project – Phase 2:
Sage north at 15th will be closed starting Wednesday for the installation of a valley gutter; please use Sage south.
Rim Road at Canyon remains closed until the concrete valley gutter installation is complete; this intersection should be open by Friday. Residents should use 6th to Quartz as the detour route.
Concrete work continues on the west side of Arroyo Lane and the north side of Verde Ridge with the primary focus on Verde Ridge in order to reopen residential parking as soon as possible. A shallow gas line was discovered on Verde Ridge and must be lowered, which will delay concrete work in a small section of Verde Ridge. No scheduled gas outage is required to complete this work.
Trenching for utility work continues on the north end of 15th Street; expect continued lane closures with flagging operations and detours as work progresses through side street intersections.