Cone Zone 05-26-13

-A A +A

Eastern Area 2 Concrete, Paving & Utility Project – Phase 2:
RMCI continues to use a 15-passenger van to transport pedestrians through the Canyon Road construction site. The van circulates every 5 to 7 minutes while RMCI is working, typically 7 a.m. to 5-7 p.m. depending on the job activity, Monday through Saturday (RMCI will work Saturdays in June). This service for pedestrians will continue until June 28 or when sidewalks are open on both sides of Canyon. Each evening, RMCI will re-establish the pedestrian paths for use.
The van route starts at 9th Street and Canyon Road continuing north on Canyon, making the Nugget, Opal and Piñon Loops. Pedestrians on Nugget, Opal, and Piñon Loops will be picked up in front of their residence. Additional stops include the Pine Street cul-de-sac and Quartz at 6th Street. The route will end at Canyon and 15th Street. The driver will then turn around and repeat the route in the opposite direction. This does not impact current school bus stops.
Canyon Road between 15th and Rim Road remains closed with a “rolling” closure; the closure may shift as work progresses. Residential access in the immediate closure area will be provided; all others motorists should seek alternate routes.
Canyon Road traffic between Nugget and Rim Road can expect daytime flagging operations with minor delays. Two-way traffic will be restored in this area in the evenings and weekends when work is not occurring.
The construction of sewer line/manhole work was postponed to May 28 and will require a closure at north Sage Loop on May 28-30. Residents are asked to use south Sage during the closure.
Mesa Public Library Safety Improvements:
Construction continues at the Mesa Public Library. The roadway in front of the library remains closed between the two library parking lots. Handicapped parking access has been moved to the Senior Center to allow the contractor to continue work on the north side of the work area. Handicapped parking at the Senior Center is accessible from Bathtub Row.
Cañada del Buey Multi-Use Trail Improvements:
The contractor continues shoulder work at the corner of Bonnieview and Longview.
Western Area Phase 1:
RMCI, Inc. will start construction on May 28. 41st and 42nd Streets north of Trinity will be closed to through traffic to allow for milling and trenching. Access to residences as well as services such as mail delivery, emergency services, and trash and recycling collection will be maintained. Residents are asked to maximize use of off-street parking. Any necessary on-street parking should be away from the existing work zone. Work hours will be Monday through Friday, 7 a.m. – 7 p.m.
White Rock Concrete Replacement:
Sections of concrete curb and gutter will be replaced on Sierra Vista, Cañada Circle, and Balboa beginning on Tuesday, May 28.
NMDOT Work on Trinity:
NMDOT will be repairing a small sink hole in the eastbound right lane, and replacing adjacent curb and gutter and sidewalk on the south side of Trinity Drive across from Ashley Pond. Expect an eastbound right lane closure Tuesday through Friday.